Project Description
SABTANK Solid Area (Section A & C) Project
Start Date:
Jul. 01, 2015
End Date:
May. 31, 2016
Location:
Jubail, Kingdom of Saudi Arabia
Your Content Goes Here
Client:
Saudi Basic Industries (SABIC) Sabtank Affiliate
SABTANK Solid Area Section ‘A & ‘C’ has conventional Fire detection and alarm system. To meet SABIC Engineering Standard and HCIS directives 2010 existing conventional Fire detection and alarm system has to converted addressable Fire detection and alarm system.
Project Goal and Scope:
- Prepare Front End Engineering package FEED which include fire hazard analysis, building code analysis, design basis, Identification of Fire Protection, Fire Detection, Alarm and design parameters, generic material, equipment specifications and all documents & drawings as required by HCIS directives (SAF-01).
Obtaining HCIS approval.